Community Solar Projects
WPPI Energy funds photovoltaic (PV) solar projects that power municipal buildings, schools, homes, businesses and more in local member communities. These projects take advantage of the sun’s abundant energy resource, while providing a highly visible demonstration of renewable energy. Solar PV projects meet the growing energy needs of our customer-owned member utilities and educate the community about the technology’s benefits, operation and performance.
WPPI Energy has provided funding and grants for the following projects:
Algoma Utilities office
- 2.7 kilowatt (kW) fixed panels
- 3,200 kilowatt-hours (kWh) per year
- PV panels: Kyocera KC200GT
- Installed by Lake Michigan Wind & Sun, Ltd.
- Output detail
Brodhead Water & Light office
- Two 2.88 kW dual-axis trackers
- 9,315 kWh per year
- PV panels: Kyocera KD180
- Installed by H & H Solar Energy Services
- Output detail
Cuba City High School
- Two 2.887 kW dual-axis trackers
- 9,880 kWh per year
- PV panels: Kyocera KD180
- Installed by H & H Solar Energy Services
- Output detail
Jefferson Area Business Center
- 21.38 kW fixed panels
- 24,800 kWh per year
- PV panels: Sharp ND-216U1F
- Installed by Carroll Electric
- Output detail
Juneau Dodgeland High School
- 5.33 kW fixed panels
- 6,600 kWh per year
- PV panels: Kyocera KC205
- Installed by H & H Solar Energy Services
- Output detail
Kaukauna 1000 Islands Environmental Center
- 5.7 kW fixed panels
- 6,930 kWh per year
- PV panels: Kyocera KD205GX-LP
- Installed by H & H Solar Energy Services
- Output detail
Kaukauna High School
- 4.9 kW fixed panels
- 5,970 kWh per year
- PV panels: Kyocera KD205GX-LP
- Installed by H & H Solar Energy Services
- Output detail
Kaukauna Utilities office
- 2.88 kW dual-axis tracker
- 4,700 kWh per year
- PV panels: Kyocera KD180
- Installed by H & H Solar Energy Services
- Output detail
Lake Mills High School maintenance building
- 10 kW fixed panels
- 12,182 kWh per year
- PV panels: Kyocera KC200
- Installed by H & H Solar Energy Services
- Co-funded by Crystal Farms Packaging
- Output detail
Little Chute Middle School
- 5.33 kW fixed panels
- 6,150 kWh per year
- PV panels: Kyocera KD205GX-LP
- Installed by H & H Solar Energy Services
- Output detail
Lodi pumphouse
- 4.5 kW fixed panels
- 5,330 kWh per year
- PV panels: Kyocera KD205
- Installed by H & H Solar Energy Services
- Output detail - coming soon
Muscoda Riverdale Elementary & Middle School
- Two 2.88 kW dual-axis trackers
- 9,680 kWh per year
- PV panels: Kyocera KD180
- Installed by H & H Solar Energy Services
- Output detail
Negaunee High School
- 10.4 kW fixed panels
- 11,300 kWh per year
- PV panels: Sharp ND-208U1
- Installed by Pieper Power
- Output detail
Oconomowoc High School
- 1.62 kW dual-axis tracker and 1.85 kW roof mount
- Together produce 4,900 kWh per year
- PV panels: Kyocera KD180 & KD200
- Installed by H & H Solar Energy Services
- Output detail
Reedsburg Area High School
- One 3.58 kW dual-axis tracker
- 6,000 kWh per year
- PV panels: Sharp 224W (NT-224U1)
- Installed by Prairie Solar Power & Light
- Output detail
Richland Center City Hall
- Three 2.88 kW dual-axis trackers
- 14,220 kWh per year
- PV panels: Kyocera KD180
- Installed by H & H Solar Energy Services
- Output detail
River Falls High School
- 3.6 kW dual-axis tracker
- 5,800 kWh per year
- PV panels: SunPower SP225
- Installed by Energy Concepts
- Output detail
Slinger Wastewater Treatment Plant
- 4.92 kW fixed panels
- 6,000 kWh per year
- PV panels: Kyocera KD205
- Installed by H & H Solar Energy Services
- Output detail
Stoughton Utilities office
- 6.8 kW fixed panels
- 8,200 kWh per year
- PV panels: Kyocera KC200
- Installed by H & H Solar Energy Services
- Output detail
Sturgeon Bay fire station
- Three 1.15 kW dual-axis tracking Solar Flairs
- 5,600 kWh per year
- PV panels: Sharp ND 072
- Manufactured and installed by Lake Michigan Wind & Sun, Ltd.
- Output detail
Sun Prairie Copps Supermarket (west)
- 231 panels; total nameplate rating of 47.4 kW
- 57,000 kWh per year
- PV panels: Evergreen Solar 205W
- Installed by Energize, LLC
- Output detail
Waunakee High School
- 4.6 kW fixed panels
- 5,500 kWh per year
- PV panels: Schott ASE 275W and ASE 300W
- Output detail
Waupun Utilities office
- Two 2.8 kW dual-axis trackers
- 9,000 kWh per year
- PV panels: Kyocera KC175
- Installed by H & H Solar Energy Services
- Output detail
Westby Bekkum Memorial Library
- 6.97 kW fixed panels
- 8,764 kWh per year
- PV panels: Kyocera KC205
- Installed by H & H Solar Energy Services
- Output detail
WPPI Energy corporate office
- Two 2.8 kW dual-axis trackers
- 9,000 kWh per year
- PV panels: Kyocera KC175
- Installed by H & H Solar Energy Services
- Output detail
|
|